The South Main Street bridge in Elmira is expected to be completed on schedule
Elmira, New York – According to the latest update from Director of Public Works Andy Avery Completion of the South Main, Street bridge in Elmira is expected to be completed on schedule.
The last bridge deck panel pour is scheduled for Thursday, Avery said. There is a 28-day cure requirement and it is anticipated the contractor will open the bridge to traffic the first week of January or sooner, once the pour is complete.
After traffic is opened, Sidewalk construction on the bridge will continue.
The project was originally scheduled to be completed in mid-December and has been closed since March 2021.
Officials have pointed towards pandemic-related causes for the delays, such as increased supply costs and shipping delays.
By the end of the year, The Lake Street Bridge project is also expected to be completed.
-
Local News2 weeks ago
Rochester hospitals make emergency plans in anticipation of the solar eclipse
-
New York2 weeks ago
In advance of the total solar eclipse, Governor Hochul provides safety advice
-
Local News2 weeks ago
Gannett should provide D&C journalists with more compensation and job security
-
Local News2 weeks ago
Hotels in the Rochester region ready for surge of eclipse fans
-
Local News1 week ago
Following an ATV accident, a man was rescued from Flint Creek
-
Local News2 weeks ago
A total solar eclipse brings families together from all across the nation
-
Local News5 days ago
Reunited Afghan family in Rochester after almost ten years apart
-
Local News1 week ago
The New York measure would alter the way that auto warranty service is paid for